3rd MAY PROGRESS REPORT ON No.5

Another evening working party took place last night at Port St. Mary with Association volunteers continuing their work on No.5 concentrating on reassembly and painting; in addition to working inside the frames as we get closer to the point when the boiler can be refitted, the first coat of green undercoat was applied to the fireman's' side tank and various other areas.  The next working group will be on SATURDAY 7th MAY in the goods shed; as ever if you can assist in our endeavours we would be delighted to hear from you on granttaylor@manx.net