ANOTHER WORKING DAY, 28th JANUARY

Association volunteers were again on site at Port St. Mary yesterday continuing work on No.5 with work including bolting the boiler down at the smokebox end and adjusting the tank brackets.  The anti-draft plates in the front of the cab have also been refitted, a rather awkward task.  The steel plate that supports the vacuum ejector has been fitted and a trip was made to Port Erin to borrow the seats and cab floor from sister No.6 to copy and make new sets for No.5,  There will be another working party next week on SATURDAY 4th FEBRUARY and you can contact us at granttaylor@manx.net if you are interested in getting involved or would like further information on the project's progression.